Cold water pool maintenance at Elba Carlota Beach & Golf Resort
Maintenance work will begin with the pool being emptied on February 21, 2026, and will continue until March 8 (both days included).
The work will be carried out from Monday to Saturday from 8:00 a.m. to 6:00 p.m.
The phases of the project will be as follows:
.-1st Phase: emptying the pool, 2 days.
.- 2nd Phase: cleaning the tile support and replacing missing tiles, 10
days.
.-3rd Phase: drying the replaced tiles, 2 days.
.-4th Phase: filling the pool, 2 days.