28.07.25: We are going to begin work to replace the old carpets in the hallways on floors 1 to 4, and we kindly ask you to open a work order form for this project.
The information currently available is detailed below. If you need additional information, please let me know:
Work schedule (to avoid blocking all rooms at once):
Floor 4: September 15, 2025 – November 8, 2025 – 8 areas
Floor 1: November 9, 2025 – November 29, 2025 – 3 areas
No work: November 30, 2025 – January 10, 2026
Floor 3: January 11, 2026 – March 7, 2026 – 8 areas
Floor 2: March 8, 2026 – April 18, 2026 – 4 areas
Project completion: April 19, 2026Nature of the work:
Removal of old carpet, removal of adhesives, preparation of the floor, and installation of new carpet.
Working method:
Each area will be isolated with screens. Guests will be able to see the workers entering the work areas, but will not see the work itself.
Impact:
Possible dust limited to the work area.
Noise from carpet removal machines (no drills or heavy machinery) during the first 2 days of work in each area on each floor.
As this is an open-plan hotel, some noise may be heard in other areas; however, no significant complaints were received during similar work in previous years.
Emergency exits will remain accessible at all times.
There will be no impact on the water or electricity supply, no odors will be noticeable, and the operation of the facilities or services will not be affected.
Working hours:
Monday to Friday, from 10:00 to 17:00.
Rooms within the active work areas will be blocked off, while adjacent rooms will remain open.
No work will be carried out between November 30, 2025, and January 10, 2026; there will be no visible activity during this period.
Additional note:
We cannot guarantee that all guests will be located away from the work areas, as this will depend on occupancy, and no compensation will be provided in advance (GOGW). However, any situation that may arise will be handled on an individual basis.
28.07.25: Change in check-in time: The new check-in time will be 3:00 p.m. Kettle service in rooms: We have placed kettles with coffee and tea service in all hotel rooms. A water station is available in some hallways so guests can refill their water bottles free of charge.
12.02.25: Please be informed about upcoming works in the pool and jacuzzi area of the FunAttic, which is an adults-only area. As such, this will only impact adult-only bookings during the work period. The work is scheduled to begin on April 28th, 2025, and is expected to be completed by June 2nd, 2025. This timeline already includes allowances for potential delays.
Please note the following details regarding the work:
In terms of alternatives, our other adults-only pool will remain open, and guests are welcome to use the jacuzzis at our Lesieur Park. Given these alternatives, we will not be offering any goodwill gestures (GOGW) during this period.